One of the really major changes in MS Project 2010 (versus Project 2007 or Project 2003) is the manual setting for tasks. This means that a task can be inputted much the same as a task in Excel, just give it a name, no need for a duration and it is just listed. BUT what is really important to know is a successor manual task will not move when linked to a predecessor (as would happen in Project 2007 or Project 2003).
From my experience training people on Project I can see the possibility of the entire schedule being “fixed” in place by this manual scheduling. Will this be a problem for users not familiar with the new manual scheduling task option?