When you have a waiting time such as concrete setting it is best to use elapsed time versus working days (the concrete does not take days off). There is no button/icon to do this instead type an e before the duration e.g. 2 edays or 48 ehrs. This way a 2 day waiting time from a Friday does not delay the schedule till Wednesday (2 working days)