Friday, March 22, 2013

Project 2013 improved reports and interface

Project 2013 is now available. In many ways much the same as Project 2010 but some great new features like reports such as "Burn down"

MS Project training Toronto, Mississauga, Ontario

Bert Twomey
MS Project 2013 trainer
Mississauga, Toronto, Ontario, Canada




Friday, January 11, 2013

In Project 2010 it is possible to change the duration of a summary task (this was not possible in earlier versions). So if a summary task is 6 days as task 1, 2 & 3 are 2 days and in a sequence then you can change the 6 days to 1 days BUT ask yourself does it make sense. Project 2010 changes the summary task to a Manually scheduled task - you can also switch it back to Auto to get the true duration
MS Project 2010, Summary Tasks & Duration

Bert Twomey
MS Office & MS Project trainer
Mississauga, Toronto, Ontario