The leveling options in MS Project 2010 are more visible as they are on the ribbon but they work the same. Is it a good thing these options are right in front of the users?
Yes & no I would say:
Yes - good that they can see these tools are available
But - no you cannot just push a button and Project 2010 (or Project 2007) solve all your problems (and if it can let me know who you work as I want a job there)
Always use the Leveling Gantt to see what Project does (Project 2010 or Project 2007)
If a resource is working full time on a few tasks then the leveling tool will help BUT if the resource is working 6 hrs a day on task a and at the same time 6 hrs a days on task b if will delay task b till after task a - so the person will only work 6 hrs a day (versus 6 hrs/day on Project task a and 2 hrs/day on task b.