Deadlines do show in Project as a downward point arrow BUT constraints do not. However it possible to insert a shape (oval for example) on the Gantt Chart tied to the specific date. In Project 2003/2007 use the Drawing toolbar to insert a shape or Project 2010 Format tab - Drawing group. Right click on the shape and select Properties and link the shape to a date - the shape shows the constraint on the Gantt chart