Friday, March 22, 2013
Friday, January 11, 2013
In Project 2010 it is possible to change the duration of a summary task (this was not possible in earlier versions). So if a summary task is 6 days as task 1, 2 & 3 are 2 days and in a sequence then you can change the 6 days to 1 days BUT ask yourself does it make sense. Project 2010 changes the summary task to a Manually scheduled task - you can also switch it back to Auto to get the true duration
MS Project 2010, Summary Tasks & Duration
Bert Twomey
MS Office & MS Project trainer
Mississauga, Toronto, Ontario
MS Project 2010, Summary Tasks & Duration
Bert Twomey
MS Office & MS Project trainer
Mississauga, Toronto, Ontario
Wednesday, March 28, 2012
MS Project 2010, Project 2007 elapsed time in Projects
When you have a waiting time such as concrete setting it is best to use elapsed time versus working days (the concrete does not take days off). There is no button/icon to do this instead type an e before the duration e.g. 2 edays or 48 ehrs. This way a 2 day waiting time from a Friday does not delay the schedule till Wednesday (2 working days)
MS Project 2010, Project 2007 Training Toronto, Mississauga, Ontario
Bert Twomey
MS Project 2010 Trainer Toronto, Mississauga
MS Project 2010, Project 2007 Training Toronto, Mississauga, Ontario
Bert Twomey
MS Project 2010 Trainer Toronto, Mississauga
Wednesday, August 31, 2011
MS Project 2007, 2010 Training Toronto Deadlines & Warning
Deadlines do show in Project as a downward point arrow BUT constraints do not. However it possible to insert a shape (oval for example) on the Gantt Chart tied to the specific date. In Project 2003/2007 use the Drawing toolbar to insert a shape or Project 2010 Format tab - Drawing group. Right click on the shape and select Properties and link the shape to a date - the shape shows the constraint on the Gantt chart
MS Project 2003/2007/2010 Training Toronto Mississauga Ontario
Bert Twomey
MS Project Training
Toronto, Mississauga Ontario Canada
MS Project 2003/2007/2010 Training Toronto Mississauga Ontario
Bert Twomey
MS Project Training
Toronto, Mississauga Ontario Canada
Thursday, May 5, 2011
MS Project 2007, 2010 Training Toronto Cost Resources
In MS Project 2007/2010 it is possible to have Cost resources (for example travel cost or car rental etc). When you add the resource just switch the Type to Cost. The advantages are: easy to see and analyze costs and when assigned to a task do not change the duration. Click on MS Project 2007, 2010 Training Toronto Cost Resources
Bert Twomey
MS Office & Project Trainer
Toronto, Mississauga
Bert Twomey
MS Office & Project Trainer
Toronto, Mississauga
Friday, March 18, 2011
MS Project Training Critical Path Toronto, Mississauga,
Critical Path in MS Project is often misunderstood and it is easy to see why. The word critical normally means more important to most people BUT not so in MS Project where it means the track that takes more time. These tasks will show in red but could be not important at all - just take longer.
MS Project Training Critical Path Toronto, Mississauga
Bert Twomey
MS Project Trainer
Toronto, Mississauga
MS Project Training Critical Path Toronto, Mississauga
Bert Twomey
MS Project Trainer
Toronto, Mississauga
Monday, February 28, 2011
Microsoft Project 2010 exam, Toronto, Mississauga
I have just passed the Microsoft Project 2010 exam and am really happy about that. Of course not everyone needs to or has to take the Project exam but if you are using Project a lot it gives you a good idea of what you should know. Look at:
Microsoft Project 2010 exam, Toronto, Mississauga
Bert Twomey
MS Project Trainer
Toronto
Microsoft Project 2010 exam, Toronto, Mississauga
Bert Twomey
MS Project Trainer
Toronto
Thursday, February 10, 2011
MS Project 2007/2010 Training Toronto Manual Task settings
In MS Project it is possible to have Manual task settings so the task will not move - much like a cell in Excel. Click on MS Project 2007/2010 Training Toronto Manual Task
BUT becareful if you need an accurate update
Bert Twomey
MS Project Trainer
BUT becareful if you need an accurate update
Bert Twomey
MS Project Trainer
Tuesday, February 1, 2011
MS Project 2010 Team Planner View Toronto Training
In MS Project 2010 there is a new Team Planner View Toronto Training which enables you to see and assign resources in a more graphical way. You simple drag and drop the resources to assign them to tasks and it is easier to see who is working on what in MS Project 2010 resource planning. Take a look at the link below for more Project training
MS Project Team Planner View Toronto Training
Bert Twomey
MS Project trainer
Toronto Mississauga Ontario
MS Project Team Planner View Toronto Training
Bert Twomey
MS Project trainer
Toronto Mississauga Ontario
Friday, January 28, 2011
MS Project 2007 2010 Driver tool
The "Driver" tool has been added to MS Project 2007 & 2010, this tool shows you what "drives" a task, such as another task, a constraint etc
http://www.actionebiz.com/projecttraining.htm for more training
Bert Twomey
MS Office & Project Trainer
http://www.actionebiz.com/projecttraining.htm for more training
Bert Twomey
MS Office & Project Trainer
Monday, January 24, 2011
MS Project 2007, Project 2010 Training Toronto, Mississauga, Hamilton Ontario
One feature that is not clearly visible in MS Project 2007 or Project 2010 is automatic text formatting. Go to the Formatting tab of MS Project 2007 Project 2010 and on the left you will see Text styles. Click this Project button and you will be able to apply a text colour or background based on a criteria such as MS Project Summary tasks. This will help people understand the data more clearly.
Click on MS Project 2007, Project 2010 Training, Toronto, Mississauga, Hamilton -, Ontario
to see more MS Project training topics
Bert Twomey
MS Project 2007/2010 trainer
Click on MS Project 2007, Project 2010 Training, Toronto, Mississauga, Hamilton -, Ontario
to see more MS Project training topics
Bert Twomey
MS Project 2007/2010 trainer
Tuesday, January 4, 2011
Leveling in MS Project 2010
The leveling options in MS Project 2010 are more visible as they are on the ribbon but they work the same. Is it a good thing these options are right in front of the users?
Yes & no I would say:
Yes - good that they can see these tools are available
But - no you cannot just push a button and Project 2010 (or Project 2007) solve all your problems (and if it can let me know who you work as I want a job there)
Always use the Leveling Gantt to see what Project does (Project 2010 or Project 2007)
If a resource is working full time on a few tasks then the leveling tool will help BUT if the resource is working 6 hrs a day on task a and at the same time 6 hrs a days on task b if will delay task b till after task a - so the person will only work 6 hrs a day (versus 6 hrs/day on Project task a and 2 hrs/day on task b.
please visit my training site
http://www.actionebiz.com/projecttraining.htm
Yes & no I would say:
Yes - good that they can see these tools are available
But - no you cannot just push a button and Project 2010 (or Project 2007) solve all your problems (and if it can let me know who you work as I want a job there)
Always use the Leveling Gantt to see what Project does (Project 2010 or Project 2007)
If a resource is working full time on a few tasks then the leveling tool will help BUT if the resource is working 6 hrs a day on task a and at the same time 6 hrs a days on task b if will delay task b till after task a - so the person will only work 6 hrs a day (versus 6 hrs/day on Project task a and 2 hrs/day on task b.
please visit my training site
http://www.actionebiz.com/projecttraining.htm
Tuesday, May 25, 2010
Gantt Chart and timeline in Project 2010
While Project has always shown the Gantt chart (which is really a visually representation of the Tasks to be completed) a new view in Project 2010 is Gantt with Timeline which shows the regular Gantt chart and also a timeline on top. The timeline shows the tasks either in a line or as callouts. This timeline can also be easily saved as a graphic and used in other documents such as PDFs, PowerPoint, Word etc.
Bert Twomey
MS Project Trainer
Bert Twomey
MS Project Trainer
Thursday, May 13, 2010
MS Project 2010 versus MS Project 2007, Project 2003 etc
Having trained and consulted on MS Project for many years I always looked forward to the release of each new version 2003, 2000, 97 etc. as features were improved but the interface (generally) stayed much the same. With MS Project 2010 there are radical new ways of using the software, for instance you can manually schedule tasks. With manual scheduling the task is locked in a time slot versus moving with the links to other tasks (dynamic scheduling). Of course dynamic scheduling is still there but not always applied - dynamic scheduling is covered in http://www.actionebiz.com/projecttraining.htm. Also until MS Project 2010 all versions of Project used the default blue colours for Gantt bar, in Project 2010 many different colour schemes are possible