Tuesday, November 8, 2011

MS Project 2007, 2010 Training Toronto Cost Resources

In MS Project 2007 & 2010 it is possible to have Cost resources (such as Hotel & Travel). Just List the Cost Resource in the Cost Sheet and click the Type from Work to Cost. MS Project 2007 & 2010 Cost resources

Bert Twomey
MS Project trainer

Wednesday, August 31, 2011

MS Project 2007, 2010 Training Toronto Deadlines & Warning

Deadlines do show in Project as a downward point arrow BUT constraints do not. However it possible to insert a shape (oval for example) on the Gantt Chart tied to the specific date. In Project 2003/2007 use the Drawing toolbar to insert a shape or Project 2010 Format tab - Drawing group. Right click on the shape and select Properties and link the shape to a date - the shape shows the constraint on the Gantt chart
MS Project 2003/2007/2010 Training Toronto Mississauga Ontario

Bert Twomey
MS Project Training
Toronto, Mississauga Ontario Canada


Thursday, May 5, 2011

MS Project 2007, 2010 Training Toronto Cost Resources

In MS Project 2007/2010 it is possible to have Cost resources (for example travel cost or car rental etc). When you add the resource just switch the Type to Cost. The advantages are: easy to see and analyze costs and when assigned to a task do not change the duration. Click on MS Project 2007, 2010 Training Toronto Cost Resources

Bert Twomey
MS Office & Project Trainer
Toronto, Mississauga

Friday, March 18, 2011

MS Project Training Critical Path Toronto, Mississauga,

Critical Path in MS Project is often misunderstood and it is easy to see why. The word critical normally means more important to most people BUT not so in MS Project where it means the track that takes more time. These tasks will show in red but could be not important at all - just take longer.
MS Project Training Critical Path Toronto, Mississauga

Bert Twomey
MS Project Trainer
Toronto, Mississauga

Monday, February 28, 2011

Microsoft Project 2010 exam, Toronto, Mississauga

I have just passed the Microsoft Project 2010 exam and am really happy about that. Of course not everyone needs to or has to take the Project exam but if you are using Project a lot it gives you a good idea of what you should know. Look at:
Microsoft Project 2010 exam, Toronto, Mississauga

Bert Twomey
MS Project Trainer
Toronto

Wednesday, February 23, 2011

MS Project 2010 Training Toronto, Mississauga, Update a Project

Hard to see and hidden in the Project tab is the option to "Update Project". This allows you to take all or some of the incomplete work and push it forward to a future date. Very useful in case you have to stop work on a project or a strike etc. Take a look at MS Project 2010 Training Toronto, Mississauga, Update a Project
for more options re training

Bert Twomey
MS Project Trainer

Monday, February 14, 2011

MS Project Training Toronto, Mississauga, track costs

You can track costs in MS Project Training Toronto using track costs. Give a resource an hourly rate and Project works out the rest

MS Project Training Toronto Mississauga

Bert Twomey
MS Project Trainer

Thursday, February 10, 2011

MS Project 2007/2010 Training Toronto Manual Task settings

In MS Project it is possible to have Manual task settings so the task will not move - much like a cell in Excel. Click on MS Project 2007/2010 Training Toronto Manual Task
BUT becareful if you need an accurate update

Bert Twomey
MS Project Trainer

Tuesday, February 1, 2011

MS Project 2010 Team Planner View Toronto Training

In MS Project 2010 there is a new Team Planner View Toronto Training which enables you to see and assign resources in a more graphical way. You simple drag and drop the resources to assign them to tasks and it is easier to see who is working on what in MS Project 2010 resource planning. Take a look at the link below for more Project training
MS Project Team Planner View Toronto Training


Bert Twomey
MS Project trainer
Toronto Mississauga Ontario

Friday, January 28, 2011

MS Project 2007 2010 Driver tool

The "Driver" tool has been added to MS Project 2007 & 2010, this tool shows you what "drives" a task, such as another task, a constraint etc
http://www.actionebiz.com/projecttraining.htm for more training

Bert Twomey
MS Office & Project Trainer

Monday, January 24, 2011

MS Project 2007, Project 2010 Training Toronto, Mississauga, Hamilton Ontario

One feature that is not clearly visible in MS Project 2007 or Project 2010 is automatic text formatting. Go to the Formatting tab of MS Project 2007 Project 2010 and on the left you will see Text styles. Click this Project button and you will be able to apply a text colour or background based on a criteria such as MS Project Summary tasks. This will help people understand the data more clearly.
Click on MS Project 2007, Project 2010 Training, Toronto, Mississauga, Hamilton -, Ontario
to see more MS Project training topics

Bert Twomey
MS Project 2007/2010 trainer

Tuesday, January 4, 2011

Leveling in MS Project 2010

The leveling options in MS Project 2010 are more visible as they are on the ribbon but they work the same. Is it a good thing these options are right in front of the users?
Yes & no I would say:
Yes - good that they can see these tools are available
But - no you cannot just push a button and Project 2010 (or Project 2007) solve all your problems (and if it can let me know who you work as I want a job there)
Always use the Leveling Gantt to see what Project does (Project 2010 or Project 2007)
If a resource is working full time on a few tasks then the leveling tool will help BUT if the resource is working 6 hrs a day on task a and at the same time 6 hrs a days on task b if will delay task b till after task a - so the person will only work 6 hrs a day (versus 6 hrs/day on Project task a and 2 hrs/day on task b.